PDCCI raise concerns on delay in road construction-package 2, Chakhabama to Kikruna NH-29

The Phek District Chamber of Commerce and Industry (PDCCI) has expressed serious concern over the persistent lack of progress in the construction of the Chakhabama Kikruma road section under Package 2, which forms part of the Kohima-Jessami road and

BY / Wednesday, 14 May, 2025

CPO 2 lane Committee directs NHIDCL to speed up construction of Kohima to Jessami Road

The CPO 2 lane Committee from Kohima to Jessami Road has expressed deep anguish over the total negligence at package 2 by NHIDCL and the Ratna company for not initiating works. “It is observed that NHIDCL is not serious

BY / Thursday, 27 February, 2025

Chakhesang Public Org express dissatisfaction with NHIDCL, EPC companies over ‘broken commitment’

Phek: Public have tolerated all for want of good roads and not out of ignorance: CPO

BY / Monday, 18 November, 2024

Phek: CSU suspends agitation for 15 days following assurance from NHIDCL

Phek: CSU says it will remain vigilant and continue to monitor progress closely

BY / Thursday, 24 October, 2024

Chakhesang Students’ Union gives NHIDCL 48 hrs to repair roads

Phek: CSU urges for clearing landslide debris, filling potholes, installing drainage

BY / Wednesday, 16 October, 2024

NPP Phek seeks immediate termination of Kohima-Jessami Road Package –II contractor

Phek: Impending rock fall between Chakhabama and Kikruma a death threat to commuters: NPP

BY / Friday, 9 August, 2024

TR Zeliang says inadequate man-power, machinery, material causing delays in Kohima-Jessami Road project

Kohima: Packages-2 and 5 project terminated, bid for construction of balance work under evaluation

BY / Tuesday, 12 September, 2023

DC Phek notifies on temporary restrictions of all vehicles on NH-29 between Kidima and Kikruma

Phek: Travelers advised to take alternative route via Zuketsu-Kidima until further notice

BY / Saturday, 19 August, 2023

NHIDCL Project NH-29 Kohima-Jessami Road: Having experienced 60 landslides in 2022, Kikruma Village appeals for resumption of works before onset of monsoon

Kikruma: NHIDCL official who worked in Phek says most works in Phek district under completion or completed

BY / Saturday, 3 June, 2023